The walls go up at ACC Maple Tree Village in Sacramento!

Reeve-Knight Project Engineer Kody Scoble takes us on a construction tour of ACC Maple Tree Village in Sacramento. Workers from different trades are laying the plumbing, building forms for the foundation, pouring concrete, and assembling prefabricated walls. The worksite is loud and bustling with activity, but there is a prevailing sense of calm and certainly as workers do what they do best.

The first wall of the North Section went up on October 24. A crew of 15 workers will complete the framing of the ground floor by the end of November. Kody says their goal is to complete enough of the structure in December, so they can work indoors during the rainy season.

Building ACC Maple Tree Village requires the precise coordination of materials and manpower. Right now there is only one entrance to the site, which makes the movement of heavy equipment in and out a challenge. But Kody and his team make it look like a well-choreographed ballet.

For more information, visit ACC Maple Tree Village. To get on our prospective applicant list, visit http://tinyurl.com/MTV-List1.

Add a Comment

Your email address will not be published. Required fields are marked *